| 2006.6 | proposal submission --> stage-1 approval | 1st PAC | |
| 2007.1 | stage-2 approval | 2nd PAC | |
| 2009.1 | completion of the beam-line spectrometer | ||
| 2009.2 | first beam to the K1.8BR beam-line | RUN#22 | |
| 2009.10 | beam-line commissioning | RUN#26, 0.040kW, 6.5h | |
| 2009.11 | beam-line commissioning | RUN#27, 0.056kW, 14.8h | |
| 2009.12 | beam-line commissioning | RUN#28, 0.16-0.55kW, 20.0h | |
| 2010.1-2 | beam-line commissioning | RUN#29, 0.32-1.0kW, 50h | |
| 2010.2 | beam-line commissioning | RUN#30, 1.0-1.6kW, 55.4h | |
| 2010.4 | completion of the cylindrical detector system (CDS) | ||
| 2010.10 | beam-line commissioning, CDS commissioning | RUN#35,0.96-3.0kW, 89.5h | |
| 2010.11 | completion of the 3He-target system | ||
| 2010.11 | (E17) SDD commissioning | RUN#36, 3.0-3.6kW, 29.5h | |
| 2012.2 | beam-line commissioning for 1.0 GeV/c, CDS commissioning | RUN#40, 1.2-3.3kW, 148.5h | |
| 2012.4 | completion of the neutron counter --> ready to run | ||
| 2012.6-7 | engineering run | RUN#43, 3.5-6.0kW, 100.5h | |
| 2012.12 | engineering run | RUN#45, 6.5-11kW, 26.7h | |
| 2013.1 | engineering run | RUN#46, 15kW, 22.8h | |
| 2013.3 | 1st-production run | RUN#47, 14.5kW, 51.5h | |
| 2013.4 | (E31) completion of the D2/H2-target system | ||
| 2013.4-5 | calibration run | RUN#49a, 11-15kW, 16.3h | |
| 2013.5 | 1st-production run | RUN#49c, 15.5-24kW, 105.1h | PTEP(2015)061D01, PTEP(2016)051D01 |
| 2015.4-5 | calibration run (H2/D2 targets) | RUN#62, 3-27kW, 160.3h | |
| 2015.10-11 | commissioning run | RUN#64, 32/39kW, 12.8h | |
| 2015.11-12 | 2nd-production run | RUN#65, 39/42kW, 676.7h | PLB789(2019)620, PRC102(2020)044002, PRC110(2024)014002 |
| 2016.5 | (E31) system launch for E31-1st | RUN#68, 42kW, 6.7h | |
| 2016.6 | (E31) 1st-production run & (E62/E57) commissioning | RUN#69(E31)/(E62/E57), 41kW, 207.7h | |
| 2017.4 | (E31) system launch for E31-2nd | RUN#74, 42kW, 12.0h | |
| 2018.1-2 | (E31) 2nd-production run | RUN#78, 45/50kW, 515.5h | PLB837(2023)137637 |
| 2018.6 | (E62) production run | RUN#79, 51kW, 431h | PRL128(2022)112503 |
| 2019.2-3 | (E57) commissioning run | RUN#81, 51kW, 103h | 2019.4 | (E57) pilot run with H2 | RUN#82, 51kW, 42h | 2020.6 | (T77) pilot run with 4He | RUN#85, 51kW, 74.2h | PLB845(2023)138128 | 2021.5 | (E73) Stage-1 with 3He | RUN#87, 64kW, 116h | PLB873(2026)140163 | 2023.6 | (T98) dbar tune | RUN#90, 50kW, 6.5h | 2024.4-6 | (E73) Stage-2 with H2/4He/3He, (E72), (T103) | RUN#91, 49-82kW, 276h | 2025.1-2 | (E73) Stage-2 with 4He/3He, (T98) | RUN#92, kW, h | 2025.11 | (E72), (E45) | RUN#93, kW, h | 2026.4 | (E72), (E45),(E104) | RUN#93, kW, h |